Training Facility Construction

 

Day 0

An empty piece of farmland

Day 1

Framing is dropped off and the post-holes are drilled

Day 2

¾ of the posts have been installed

Day 3

Posts are finished and the walls are framed out

 

 

Doors have been framed out

 

 

Started to install the siding

 

 

 

Half of the trusses are up

 

 

Day 4

Got home too late and had to take pictures in the dark

Day 5

All of the framing is complete, 2 walls have siding, doors are installed

Day 6 & 7

They Rested

(looking forward to Day 8!)

3 walls are complete

Overhead door is installed, windows on one side are in

Day 8

All of the windows are in and the trim is complete

 

 

 

View from the back

 

 

Inside

Day 9

-42C with the windchill & winds gusting to 26 mph and still ……

It’s Done!

(now Craig has to finish the inside!)

We have a floor!

Look at that!  We can actually use it now!

A huge thanks to all those who helped out finishing the inside:

Julio & Johanna, Judy & Mark, Fiona & Dwayne, Bev, Rob